Active Commuting updatesConstruction updatesRoad closures Weekly Construction Update November 16 to 20 The nice fall weather has helped crews tie up work on several projects over the last week and start on a few others. Here is what’s happening for maintenance and construction work in Beaumont this week: New projects/updates: Sanitary sewer line...
Active Commuting updatesConstruction updatesRoad closures 50 Avenue Water Feedline Construction Updated: November 16, 2026 Progress update for east of 50 Street: Paving between the St. Vital pumphouse and 48 Street is complete. Some restoration work remains at the far east end of 50 Avenue. Progress update for west of 50 Street: Feedline...
Active Commuting updatesConstruction updatesRoad closuresUtilities notice Sanitary System Improvements – 50 Avenue and 47 Street Update: November 16, 2026 Most work is complete and paving along 47 Street is finished and the road has reopened. Sidewalk and landscape restoration will take place in the spring. Update: November 9, 2026 The underground work is complete, and 47...
Commuting updatesConstruction updatesRoad closures Weekly Construction Update November 9 to 13 Crews continue to get as much work done as possible while the temperatures remaining above freezing and the ground is snow-free. Here’s what’s happening for maintenance and construction work in Beaumont this week: New projects/updates: Sanitary...
Commuting updatesConstruction updatesRoad closures Weekly Construction Update November 2 to 6 Warmer temperatures are in the forecast for the week ahead, and crews are taking advantage of this to complete construction and maintenance work. Here is what’s happening in Beaumont this week: New projects/updates: Parking lane and sidewalk...
Commuting updatesConstruction updatesRoad closures Weekly Construction Update October 26 to 30 With winter on the way, crews are busy prepping ahead of the winter season and winding down construction on final projects. Here is what’s happening in Beaumont this week: New projects/updates: 50 Avenue water feedline construction: Crews are...
Commuting updatesConstruction updatesRoad closures Weekly Construction Update October 19 to 23 After the windstorm on the weekend, crews are focused on cleaning up throughout the city this week. Here’s what else crews are up to for construction and maintenance activities around Beaumont this week: New projects/updates: 50 Avenue water...
Commuting updatesConstruction updatesRoad closures Weekly Construction Update October 13 to 16 It’s a shorter week due to the stat holiday on Monday, but here’s what crews are up to for construction and maintenance activities around Beaumont this week: New projects/updates: 50 Avenue water feedline construction: The water feedline...
Commuting updatesConstruction updatesRoad closures Weekly Construction Update October 5 to 8 Many capital projects and summer maintenance work have wrapped up, but we’re still taking advantage of the warm weather and last few weeks of fall to finish several projects and maintenance work. Here’s what’s happening around Beaumont this...
Commuting updatesConstruction updatesRoad closures Weekly Construction Update September 28 to October 2 The construction season is quickly winding down, but things around Beaumont certainly aren’t stopping any time soon. Here’s what to expect for activity around Beaumont this week: New projects/updates: 50 Avenue water feedline...