Aqua-Fit Phase 2 Project

New Sports Facility


The land next to the Aqua-Fit Centre, which is currently the temporary dog park, will eventually be developed into a new sports facility. We call this project Aqua-Fit Phase 2.

Social Media 


Follow us on social media: Facebook or Twitter. Sign up for the Our Beaumont mailing list by emailing us.

Timeline of the Project

 
  • August 23, 2016: Council approved a Project Charter (conceptual and detail design) for the Aqua-Fit Phase 2 that defines the scope of the project; the approval processes; project schedule, communications and to identify and analyze project risks and mitigation strategies.
  • November 2016: Town engaged BR2 Architecture after a competitive RFP process.
  • December 2016 to March 2017: Town staff and BR2 are working towards reconfirming information on work completed to date, work with users/public to develop up to 3 high-level schematic designs for Council consideration and to move forward with conceptual design.
  • March 20, 22, and 27, 2017: BR2, Focus Communications and Beaumont staff hosted Community Public open house input meetings.
  • March 28, 2017: Council selected preferred option #3 for conceptual design of the project.
  • March to July / August 2017: Complete conceptual and detailed design to the building permit stage (shovel ready project).
  • June 27: Council approved the reduced scope at $29,500,000.
  • July/August 2017: BR2 to complete operating models, meet with stakeholders and complete the detailed design.
  • Fall 2017: Council will consider the budget request for the Aqua-Fit based on the detailed design moving forward. 
There will significant opportunity for the public and users to comment on the project throughout the process.